OCR Text |
Show 4920 Cleary- C 2933 construction, which are the things that only precede approval of construction. Q Just what would that mean? A I don't understand you. Q Just what would that be, that additional survey? A It would have been the staking of the route ahead of the construction. Q It is the actual staking? A Absolutely. Q You wouldn't show that on the map necessarily, would you, at all? A Yes, certainly. Q would that be an additional survey? A It would. Q You didn't stake this route, then? A I did. Q You would put in more stakes later? A I would put in more stakes later; I would change around somewhat. Q And make a survey for that purpose? A Yes sir, preceding construction, sir. It takes three surveys, generally. Q Where, with respect to the lines shown on these Exhibit 464, 464 A and 464 B, respectively, was the proposed route of the pipe line? |